PK1-003 Exam

CompTIA Project+ Certification (BETA Exam)

  • Exam Number/Code : PK1-003
  • Exam Name : CompTIA Project+ Certification (BETA Exam)
  • Questions and Answers : 240 Q&As
  • Update Time: 2011-10-24
  • Testing Engine (SoftWare Version): $ 89.00
  • PDF (Printable Version) Price: $15.00
  •  

Note: After purchase, we will send questions within 24 hours.

Free PK1-003 Demo Download

Hiexam offers free demo for Project+ PK1-003 exam (CompTIA Project+ Certification (BETA Exam)). You can check out the interface, question quality and usability of our practice exams before you decide to buy it. We are the only one site can offer demo for almost all products.

Download PK1-003 Exam Testing Engine

 

Exam Description

Why choose Hiexam PK1-003 braindumps

Quality and Value for the PK1-003 Exam
100% Guarantee to Pass Your PK1-003 Exam
Downloadable, Interactive PK1-003 Testing engines
Verified Answers Researched by Industry Experts
Drag and Drop questions as experienced in the Actual Exams
Practice Test Questions accompanied by exhibits
Our Practice Test Questions are backed by our 100% MONEY BACK GUARANTEE.

Hiexam PK1-003 Exam Features

- Covers the entire recommended syllabus
- Comprehensive questions and answers about PK1-003 exam
- Verified Answers Researched by Industry Experts and almost 100% correct
- PK1-003 exam questions updated on regular basis
- Same type as the certification exams, PK1-003 exam preparation is in multiple-choice questions (MCQs)
- Tested by multiple times before publishing
- Try free PK1-003 exam demo before you decide to buy it in Hiexam
- Technical support through Live Chat or Email

 
 
Exam : CompTIA PK1-003
Title : CompTIA Project+ Beta Exam


1. Who has the MOST influence over project decisions?
A. Project team members
B. End users
C. Key stakeholders
D. Project manager
Answer: C

2. Which of the following activities would happen LAST in procurement management?
A. Request seller responses
B. Perform contract administration
C. Perform vendor selection
D. Perform a make or buy analysis
Answer: B

3. Which of the following is the purpose of a Pareto diagram?
A. To show the sequence in which work will be performed
B. To create the process that will complete the project
C. To determine the critical path
D. To direct team efforts to the areas that will have the most impact
Answer: D

4. A project manager is in a projectized organization managing a particular project. A department manager has repeatedly requested a change to the scope of the project which was previously denied. The project is currently behind schedule. Which of the following would be the BEST way to deal with the managers repeated request?
A. Request the manager fill out a formal request for the change and file it with the project management office.
B. Have a team member meet with the manager so the project can stay on schedule.
C. Ask the project sponsor to respond to the department manager.
D. Implement the change as requested by the manager and inform the project sponsor.
Answer: C

5. Design, launch, review and test are examples of which of the following work breakdown structure (WBS) schemes?
A. Functions
B. Organizational units
C. Product components
D. Geographical areas
Answer: A